In 2021, for the first year ever, we worked in three communities, two water projects, in the communities of Mancera Central and Bilampi, and one School project in the community of Malakawas. We also initiated a pilot After-School Club in the community of El Aulo! The projects will bring clean water and education to over 650 people!
Mancera Central Water Project: Benefiting 50 families
Currently completing the final suspension bridge, which will complete the water distribution system. The next item would be to build the latrines in each household!
Malakawas – School: Benefiting 60 families
School is complete except for hanging the classroom divider which is already constructed. We will be handing the keys to this new school in the next few days!
Bilampi – Water Project: Benefiting a community with 43 families, 2 schools, and a church
Spring Capture & Tank 100% are complete! The distribution system is 70% complete. There is 6.5 km more pipe to get into the ground. This will take two months to complete at this pace (100-150 meters per day). We estimate the water portion can be completed by early February and the latrines finished by March 2022.
Kids Turning on Water in Bilampi Community Members in Manceras Central Almost Finished School in Malakawas